Vis enkel innførsel

dc.contributor.authorMørck, Ingjerd
dc.contributor.authorThorsen, Simen
dc.contributor.authorGrøv, Eivind
dc.contributor.authorTrinh, Quoc Nghia
dc.date.accessioned2023-01-11T07:36:48Z
dc.date.available2023-01-11T07:36:48Z
dc.date.created2023-01-02T09:26:23Z
dc.date.issued2022
dc.identifier.isbn978-82-8208-077-4
dc.identifier.urihttps://hdl.handle.net/11250/3042521
dc.description.abstractOslo er Europas raskest voksende by, og prognosene tilsier fortsatt kraftig vekst. 90% av Oslos vannforsyning utgjøres av Maridalsvannet og Oset vannbehandlingsanlegg. Dette konseptet gjør byens vannforsyning sårbar for hendelser knyttet til drikkevannskilden og vannbehandlingsanlegget. Oslo kommune arbeider med å etablere en fullgod reservevannforsyning innen 1. januar 2028. Det nye vannbehandlingsanlegget skal ligge på Huseby under Husebyskogen og skal bestå av seks store fjellhaller med tverrsnitt varierende mellom og 20m x 24m og 26m x 43m i tillegg til en montasjehall for TBM til råvannstunnelen. Hallene ligger i tre nivåer og utgjør et komplekst system av bergrom og tunneler. Det er mye berg, ca 850 000 m3, som skal tas ut på et relativt lite område. Det var forventet at det skulle bli komplisert å bygge berganlegget med behov for tung sikring i form av gitterbuer i kombinasjon med sprøytebetong. Tilsvarende, men mindre komplekse bergrom i nærheten er sikret på denne måten. I tillegg var det kartlagt en del svakhetssoner som var forventet å by på utfordringer. VAV som byggherre så det som nødvendig å følge nøye med på hvilken påvirkning uttak av så mye berg på et såpass lite område kunne ha for spenningsbildet i bergmassen og potensielt medføre deformasjoner i berget omkring fjellhallene. I samarbeid med Skanska ble SINTEF engasjert for å simulere utviklingen av disse parameterne før de fysiske arbeidene startet opp. Med inspirasjon fra Tripod-modellen som SINTEF har utviklet og bl.a. benyttet for BaneNOR på Follobanen, satt vi i felleskap opp et overvåkningsprogram som skal brukes for å kalibrere og verifisere modellen. Modellen har blitt brukt til å identifisere de mest kritiske partiene i anlegget og viste at hengen i hallene ikke er like kritisk som tidligere antatt i prosjekteringsfasen. Basert på kartlagte strukturer i overflaten og i tunnelene har vi beregnet de mest kritiske kilene og dimensjonert sikringen etter disse. Simuleringene og de fysiske målingene har gitt oss trygghet til å ta ned sikringsnivået betraktelig på de mest kritiske partiene. Hallene er sikret med sprøytebetong, 20 cm påført i to omganger (10 cm av gangen) og systematisk bolting med boltelengde mellom 5 og 6 m satt mellom de to omgangene med sprøytebetong. Modellen har hjulpet oss å identifisere områder som observeres ekstra nøye gjennom byggeprosessen. Det er observert lite oppsprekking eller avskalling av sprøytebetongen. Laserskanning av hallene før påføring av sprøytebetongen skal brukes for å identifisere sprekkemønster og verifisere at mulige kiler er sikret tilstrekkelig. Spenningsomlagring og deformasjoner overvåkes nå fortløpende i takt med utdrivningen og sammenliknes med forventet utvikling. Modellen kalibreres med observasjoner gjort i måleprogrammet. Dette gir prosjektet et solid beslutningsgrunnlag for å verifisere sikringsomfanget. Målingene har så langt verifisert at sikringsomfanget er tilstrekkelig for å ivareta både lokal og global stabilitet i hallene.en_US
dc.description.abstractOslo is the fastest growing city in Europe. The prognosis indicate that the population growth will continue. Today 90% of the water supply to Oslo comes for Maridalsvannet at the water treatment plant at Oset. This makes the city very vulnerable to incidents that strikes either the source or the treatment plant. The municipality of Oslo is therefore in the process of building a secondary water supply. By January 1st 2028 the new water supply to Oslo will be ready. The new water treatment plant is located at Huseby under Husebyskogen. The treatment plant consists of six large caverns with cross sections varying between 20m x 24m to 26m x 43 m. In addition, we are building an assembly chamber for the TBM that is going to excavate the water supply tunnel. The treatment plant makes three different levels and is a complex system of tunnels and caverns. The volume is approximately 100 000 m3 which is all excavated in a relatively small area. It was expected to be complicated to build the treatment plan. The plan was to use heavy rock support with arches of lattice girders in combination with rock bolts and shotcrete. Similar, but smaller and less complex caverns nearby is built using the same rock support. There was also identified several weakness zones, adding to the supposed need for lattice arches. VAV found it necessary to follow-up the effect the excavation of such a large volume on such a small area could have on the stress system in the rock mass and the potential deformations in the caverns. In collaboration with Skanska, SINTEF was engaged to model the development of the stress and strain before starting the actual excavation. Inspired by the Tripod-model that SINTEF had developed and used with e.g. BaneNOR at the Folloline project, we established a surveillance program to be used for calibration and verification of the model. The model has been used to identify the most critical areas in the caverns and to document that the roof of the caverns is not as critical for stability as first expected. Rock joints were mapped in the adjacent tunnels and available surface rock. Based on the mapped joints, the most critical wedges were identified, and the rock support decided based on the most critical wedges. The simulations and the measurements have given us the confidence to downsize the rock support in the caverns. The caverns are now supported by 20 cm thick shotcrete applied in two layers and rock bolts with length between 5 and 6 m applied between the two rounds of shotcrete. With help from the numeric model, we have identified areas that will be subject to frequent visual inspection throughout the excavating process. So far, we have fund very little fracturing or spalling of shotcrete. Before applying shotcrete, the caverns are scanned, using a LIDAR scanner. The scan will be used to identify the actual jointing of the rock mass and to verify that the most critical wedges are supported sufficiently by the applied rock support. Stress and strain are monitored continuously, and the measured values are compared to the modelled values. The model is updated and calibrated with the observations made in the surveillance program. This gives us a strong basis for deciding and verifying the rock support. So far, the measurements have confirmed that the rock support is sufficient for both local and global rock stability.
dc.language.isonoben_US
dc.publisherNorsk forening for fjellspeningsteknikken_US
dc.relation.ispartofFjellsprengningsteknikk Oslo, 24. november 2022. Bergmekanikk Oslo, 25. november 2022. Geoteknikk Oslo, 25. november 2022
dc.titleNy vannforsyning Oslo – Fjellhaller til nytt vannbehandlingsanlegg: bergsikring, deformasjon og spenningsutviklingen_US
dc.title.alternativeNew water supply Oslo – Caverns for the new water supply: rock support, stress and strain developmenten_US
dc.typeConference objecten_US
dc.description.versionpublishedVersionen_US
dc.rights.holder© 2022 The authorsen_US
dc.source.pagenumber39.1-39.21en_US
dc.identifier.cristin2098555
cristin.ispublishedtrue
cristin.fulltextoriginal


Tilhørende fil(er)

Thumbnail

Denne innførselen finnes i følgende samling(er)

Vis enkel innførsel